Regione Lombardia
Cultural Centre Turin
SKY Village
30A1 Building
Trento Court House
Bodio Centre
Maciachini Centre
Danielli's skyscraper
Milan Tech Institute
H3G Edison
H3G Da Vinci
H3G Cristoforo Colombo
RAS C.so Italia
RAS M. Gioia
RAS V.le Monza
RAS Velasca Tower
The "Galbanino"
Telecom Boscaiola
Telecom Skyscraper GE
Telecom Te Brunetti
Telecom Guidoni
Generali RE Group
BNL Roma
Sport Centre Turin

 

Turin Municipality
New Cultural Center - Turin

Commissioned by: Turin Municipality – the Culture and Museum Authority

Architectural Design: arch. Mario Bellini

Design winner of the public competition called by the Culture and Museum Authority of Turin Municipality for the realization of a New Cultural Center.

The goal of this realisation is to create a new strongly-attracting cultural facility inside the city of Turin with a 40.000sq.m library, two prose theatres (1.200 and 400 seats), a 500 seats outdoor theatre, offices, public service areas, restaurants, management services, parking lots, green areas.

In terms of energy saving the design consists in the use of underground water-table (max extraction depth 35mt - not usable for potable purpose) for HVAC use in combination with a chilled-beams system in the library areas.

During the hot season the underground water-table will be used for:

  •   the pre-chilling of the fresh air with an energy saving of about the 20% of the total frigorific load

  •   the feed of chilled-beams in the library, realising a "low-cost chilling" (the underground water-table, extracted at an almost constant temperature of 15°C, is used, previously treated by heat-exchanger, as chilling fluid in the beams, which require a temperature of 17-18°C in summer, giving an energetically free-of-charge air conditioning)

  •   the chilling of ACUs’ condensers, with a 10% decrease in electrical consumption (underground water-table allows the ACUs’ condensation at sensibly lower temperatures rather than with the use of cooling towers or air operated condensers)

The use of chilled-beam system in the library has further aspects as:

  •   soundproof system thanks to the absence of moving equipment

  •   vertical-thermal-gradient reduction

  •   high-graded physiological comfort for the occupants

Further aspect of the use of underground water-table is:

  •   removal of external technical volumes related to ACU’s condensation system (as cooling towers or air condenser systems) avoiding the relative environmental, acoustic and visual impact.

Design data:
Area: about 120.000sq.m
Frigorific power (foreseen): 8.200kW
Thermal power (foreseen): 9.400kW
HV+LV power (foreseen): 13,6 MW

works amount:  63.000.000 € - estimated (M&E Plants)

PERIOD:                 From January 2002 to July 2006