Regione
Lombardia Commissioned by: ELECA S.p.A. Executive project, winner of the public contract competition called by "Regione Lombardia", for the complete refurbishment of the M&E Plants in its head office. During the summer season, water raising from the underground water-table provides for :
The use of underground water allows lower condensation temperatures than in traditional tower water units, improving the energy efficiency of the machines and considerably reducing the electrical power input at the same frigorific power output, achieving a further 10% of energy saving of the total frigorific load. In winter, the room air-conditioning units reverse their cycle to become heat-pumps and, using the water from the underground water-table as a "heat source", they supply heating to the building with a very high energy efficiency. DESIGN
DATA: WORKS AMOUNT: 10.500.000,00 € (M&E Plants) PERIOD: From May 1997 to August 1997 |
|